Rate changes effective October 1, 2021
The total fee for permit approval shall be the sum of the below elements. An additional 25% shall be added to the total permit for applications outside the City limits for water system fees. (Ord. No. 1820)
Permit Base Fee:
- Residential or commercial or industrial-$195
- Sewer replacement-$60
- Industrial waste dischargers (SMC 13.16.21 0B)-$400
Inspection Fee:
- 2 hours x Current Inspector Burdened Rate (Minimum)-$150.00
- Additional inspection as warranted: # hours x Staff Burdened Rate
Plan Review Fee:
- 1 hour x Current Engineer Burdened Rate (Minimum)-$110.00
- In-house plan review fee + # hours x Current Engineer Burdened Rate
- Third-party review fees as billed to City, including City administrative costs
Burdened rate for City staff:
- Associate Engineer -$110.00
- Engineering Technician -$75.00
System Development Charge
per equivalent residential unit (ERU) (Ord No. 2077) – $6,150.05
- single family residence = 1.0 ERU per unit
- multi-family residence = 0.75 ERU per unit after 1st unit
- accessory dwelling units = 0.5 ERU
- retail = 1.25 ERU per 1,000 sq/ft of building
- restaurant = 0.25 ERU per occupant load
- assembly = 0.08 ERU per occupant load
- office = 0.8 ERU per 1,000 sq/ft of building
- industrial domestic = 0.1 ERU per 1,000 sq/ft of building
- High cubed warehouse = 0.03 ERU per 1,000 sq/ft of building
- mobile home park = 1.0 ERU per space
- motel = 0.65 ERU per room
- service station = 4.0 ERU
- mini-mart = 6.0 ERU
Quick Links
- Return to Permit Information & Fees
- Go to the Permit Center homepage
- Open the portal to begin /access your permit application
Contact Us
Allison Judge or Allison Judge, Development Services Specialists, 253-299-5530
To schedule inspections, please use the online portal. You will use the same login information you used to apply for your permit.
For more information on code issues, please contact the Building Official at 253-299-5530 or buildingofficial@sumnerwa.gov.